2007
2011
2012
2015
2016
2017
2018
2019
2021
2022
2023
2024
  • Ministry of Petroleum & Natural Gas approves the induction of Mittal Energy Investments Pte Ltd. (MEI).
  • The name of the company changes from Guru Gobind Singh Refinery Ltd. to HPCL-Mittal Energy Ltd. (HMEL).
  • The 1,017 km pipeline and COT commissioned and marketing network established.
  • Receipt of the first batch of crude oil.
  • GGSR dedicated to the nation by the then Prime Minister, Dr. Manmohan Singh.
  • 9 MMTPA Refinery fully commissioned and commercial production begins.
  • Environment clearance for expansion of GGSR received.
  • GGSR achieves highest ever crude throughput vis-à-vis nameplate capacity.
  • Refinery’s name-plate capacity expanded by ~25% to 11.3 MMTPA.
  • New Unit set up for the production of Bitumen.
  • Environment clearance received for Polymer Addition Project.
  • Polypropylene unit capacity enhanced to 467KTPA with commissioning of 3rd Reactor in March 2018.
  • Environment clearance received for Fuel Quality Upgradation Project (BS-VI).
  • New DHDT Unit commissioned for Fuel Quality Upgradation to BS-VI.
  • FCC Unit modified to boost capacity utilization to upto 125-130%.
  • Highest ever refinery throughput of 12.7 MMT achieved during FY-22.
  • Achieved Mechanical completion of 1.2 MMTPA Dual Feed Cracker Unit of Guru Gobind Singh Polymer Addition Project (GGSPAP).
  • Guru Gobind Singh Polymer Addition Project featuring a 1.2 MMTPA Multi-Feed Cracker along with 1.2 MMTPA Polyethylene (PE) and 0.5 MMTPA Polypropylene (PP) Plants commissioned.
  • 300 KLPD Bioethanol Plant Commissioned.